Question: You have six tasks to which need to be completed as soon as possible. Each task requires one person. There are six employees available to

You have six tasks to which need to be completed as soon as possible. Each task requires one person. There are six employees available to you to assign to these tasks. The time in hours taken the employees to do each task is shown. NQ in a cell means that the person is not qualified to that specific task. Which employee should be assigned to which task and what will be total time? (10 Points)

Employee

Task 1

Task 2

Task 3

Task 4

Task 5

Task 6

Amy

6

8

5

6

8

7

Ben

6

7

7

9

10

6

Carla

7

8

8

NQ

11

8

John

8

NQ

12

11

NQ

9

Michelle

5

10

8

7

7

8

Nancy

8

NQ

10

9

NQ

7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!