Question: You have successfully completed the Perform Quality Assurance process. Which of the following is not an output of Perform Quality Assurance? Group of answer choices
You have successfully completed the Perform Quality Assurance process. Which of the following is not an output of Perform Quality Assurance? Group of answer choices Process analysis Organizational process asset updates Change requests Project management plan updates