Question: You have to decide between projects A and project B. No project is not an option. The cash flows are as follows: Project A: t=0:
You have to decide between projects A and project B. No project is not an option. The cash flows are as follows:
Project A: t=0: -9000; t=1: -2200; t=2: 4000; t=3: 2057
Project B: t=0: -8000; t=1: -4480; t=2: 4000; t=3: 3644
Find the IRR of the incremental project. MARR=15%. Choose the best answer.
| a) | 7% |
| b) | 8% |
| c) | 9% |
| d) | 22% |
| e) | 23% |
| f) | 24% |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts