Question: You know that BAC = 375, PV = 300, AC = 200, and cumulative EV = 250. Variances that have occurred on the project to

You know that BAC = 375, PV = 300, AC = 200, and cumulative EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC?

a. 75

b. 50

c. 125

d. 150

Your hardware vendor left you a voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response strategy for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy?

a. Transfer

b. Acceptance

c. Avoid

d. Mitigate

What are the performance measurements for the Control Schedule process?

a. SV = (EV AC) and SPI = (EV / AC)

b. SV = (EV BAC) and SPI = (EV / BAC)

c. SV = (EV PV) and SPI = (EV / PV)

d. SV = (PV EV) and SPI = (PV / EV)

During which project management process group are risk and stakeholders ability to influence project outcomes the highest at the beginning of the process?

a. Planning

b. Executing

c. Monitoring and Controlling

d. Initiating

All of the following statements describe the activity list except which one?

a. The activity list includes an identifier and description of the activity.

b. The activity list is an extension of and a component of the WBS.

c. The activity list includes all activities of the project.

d. The activity list is an output of the Define Activities process.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!