Question: 9. You expect future project performance to be consistent with the project performance experienced to date for this work component. If BAC = 800, PV
9. You expect future project performance to be consistent with the project performance experienced to date for this work component. If BAC = 800, PV = 300, AC = 200, EV =250. What is the EAC?(10 points
\