Question: You may need to use the appropriate technology to answer this question. A project consists of five activities as shown in the following table. Activity

You may need to use the appropriate technology to answer this question.
A project consists of five activities as shown in the following table.
Activity Optimistic Time (hr) Most Probable Time (hr) Pessimistic Time (hr)
Floor sanding 456
Floor buffing 456
Paint mixing 0.511.5
Wall painting 3411
Ceiling painting 37.59
Naturally, the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing.
(a)
Construct the PERT/CPM network for this problem.