Question: You may need to use the appropriate technology to answer this question. A project consists of five activities as shown in the following table. Activity
You may need to use the appropriate technology to answer this question.
A project consists of five activities as shown in the following table.
Activity Optimistic Time hr Most Probable Time hr Pessimistic Time hr
Floor sanding
Floor buffing
Paint mixing
Wall painting
Ceiling painting
Naturally, the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing.
a
Construct the PERTCPM network for this problem.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
