Question: You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new

You may need to use the appropriate technology to answer this question.
Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network.
i
Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows.
\table[[Activity,Optimistic,Most Probable,Pessimistic],[A,4,8,12],[B,6,7,8],[C,6,12,18],[D,3,5,18],[E,6,15,17],[G,5,6,10]]
(a) Find the critical path. (Enter your answers as a comma-separated list.)
(b) What is the expected project completion time (in weeks)?
weeks
(c) Based only on the critical path, what is the estimated probability the project can be completed in 43 weeks as requested by the owner? (Round your answer to four decimal places.)
(d) Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 56 weeks for this calculation. (Round your answer to four decimal places.)
 You may need to use the appropriate technology to answer this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!