Question: You monitored figures on cost and planned/earned value for each individual project week (1- 6) until the date at the end of the sixth week.
You monitored figures on cost and planned/earned value for each individual project week (1- 6) until the date at the end of the sixth week. What is the status of this project at this date? Project Week # AC EV PV 1 $65,000 $61,000 $67,000 2 $85,000 $79,000 $89,000 3 $100,000 $102,000 $110,000 4 $125,000 $124,000 $121,000 5 $135,000 $133,000 $139,000 6 $125,000 $120,000 $131,000 Group of answer choices The project is behind schedule and over budget. The project is ahead of schedule and over budget. The project is ahead of schedule and under budget. The project is behind schedule and under budget