Question: Data are for 6 different weeks ( not cumulative ) You monitored figures on cost and planned / earned value for each individual project week
Data are for different weeks not cumulative You monitored figures on cost and plannedearned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date?
Project Week
Actual Costs
Earned Value
Planned Value
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
a
The project is ahead of schedule and over budget
Incorrect Response
b
The project is behind schedule and over budget
c
The project is ahead of schedule and under budget
Correct Answer
d
The project is behind schedule and under budget