Question: Data are for 6 different weeks ( not cumulative ) You monitored figures on cost and planned / earned value for each individual project week

Data are for 6 different weeks (not cumulative) You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date?
Project Week
Actual Costs
Earned Value
Planned Value
1
$75,000
$61,000
$57,000
2
$95,000
$79,000
$69,000
3
$130,000
$152,000
$160,000
4
$54,000
$74,000
$71,000
5
$205,000
$203,000
$209,000
6
$45,000
$50,000
$71,000
a)
The project is ahead of schedule and over budget
Incorrect Response
b)
The project is behind schedule and over budget
c)
The project is ahead of schedule and under budget
Correct Answer
d)
The project is behind schedule and under budget

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!