Question: You plan to compress the schedule using a one - time unit per move and the least cost method. You want to reduce the schedule

You plan to compress the schedule using a one-time unit per move and the least cost method.
You want to reduce the schedule until you reach the maximum crash point (crash duration) of the network.
You have already identified which activities to crash and the crashing order of these activities to reach the crash point.
The crashing order is the following:
Iteration 1- activity B
Iteration 2- activity B
Iteration 3- activity E
Iteration 4- activity C
Iteration 5- activity D
What will the total cost of the project be after iteration 1?
You can use the Excel file Q66-Schedule Crashing as a helping tool. No need to upload the solution in Excel.
Answer:
Question 67
Not yet answered
Marked out of 1.0
Flag question
Question text
What will the cost of the project be after iteration 2?
Answer:
Question 68
Not yet answered
Marked out of 1.0
Flag question
Question text
What will the cost of the project be after iteration 3?
Answer:
Question 69
Not yet answered
Marked out of 1.0
Flag question
Question text
What will the cost of the project be after iteration 4?
Answer:
Question 70
Not yet answered
Marked out of 1.0
Flag question
Question text
What will the cost of the project be after iteration 5?
Answer:
Question 71
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the project duration at the crash point?
a.
23 weeks
b.
20 weeks
c.
24 weeks
d.
21 week
e.
22 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!