Question: You plan to compress the schedule using a one - time unit per move and the least cost method. You want to reduce the schedule

You plan to compress the schedule using a one-time unit per move and the least cost method.
You want to reduce the schedule until you reach the maximum crash point (crash duration) of the network.
You have already identified which activities to crash and the crashing order of these activities to reach the crash point.
The crashing order is the following:
Iteration 1- activity B
Iteration 2- activity B
Iteration 3- activity E
Iteration 4- activity C
Iteration 5- activity D
What will the total cost of the project be after iteration 1?