Question: You signed a contract to build a building. Draw the project network and compute total slack and free slack for each activity. ID A B

You signed a contract to build a building. Draw

You signed a contract to build a building. Draw the project network and compute total slack and free slack for each activity. ID A B D E F G H I J Description Foundation Erect Frame Roof Windows Doors Electrical Rough-in frame Predecessor None A B B B B C, D, E, F E, F G, H I Time (DAYS) 3 4 4 1 1 3 2 1 2 1 Door opener Paint cleanup