Question: You timed a task for 7 0 cycles. The average time per cycle was 1 0 . 2 minutes. The worker had a performance rating

You timed a task for 70 cycles.
The average time per cycle was 10.2 minutes.
The worker had a performance rating of 116%.
Assume an allowance of 11% of workday time.
What is the observed time? minutes
What is the performance rating?
What is the allowance, A?
Which allowance factor is being used?
What is the allowance factor?
What is the normal time? minutes
What is the standard time? minutes