Question: You will be best served by doing this exercise by hand. For two questions, please provide clean and neat diagrams, clearly labeled, with short, well-worded
You will be best served by doing this exercise by hand. For two questions, please provide clean and neat diagrams, clearly labeled, with short, well-worded answers to each question.
Question 1:
Draw a project network diagram from the following information. What is the expected duration of the project?
| Activity | Predecessor | Duration (weeks) |
| A | None | 2 |
| B | A | 4 |
| C | A | 3 |
| D | A | 2 |
| E | B | 3 |
| F | C | 6 |
| G | C, D | 5 |
| H | E, F | 6 |
| I | G | 5 |
| J | F, G* | 4 |
| K | H, I, J | 5 |
| L | K | 1 |
* Work on activity J can begin any time, but cannot be completed before F &G are complete (in other words, this represents a Finish-to-Finish relationship with F and G).
Question 2: Suppose that the project in Question 1 of Exercises #2 is staffed by four team members: A manager (MGR), a designer (DES), an Engineer (ENG), and a Technician (TECH). The activities require the following staffing:
| Activity | Staff Required* |
| A | MGR, DES, ENG, TECH |
| B | DES |
| C | ENG |
| D | TECH |
| E | DES, ENG (requires 50% of each employees time during this activity)** |
| F | ENG |
| G | ENG, TECH (requires 50% of each employees time during this activity) |
| H | DES, ENG |
| I | TECH |
| J | TECH (ENG and/or DES can complete up to 50% of the work) |
| K | DES, ENG, TECH |
| L | MGR |
*Unless otherwise noted, all activities assume 100% time dedication of the assigned employee(s).
**When multiple resources are listed, those resources are required for that activity at the same time.
Create a histogram for each of the three employees (not MGR) to show the demands on their time.
Please help and thank you!