Question: You will need to save the Excel file you create to solve this problem as it will need to be submitted ( uploaded ) as

You will need to save the Excel file you create to solve this problem as it will need to be submitted (uploaded) as part of your overall solution.
A project is composed of five activities (A, B, C, D, and E). Suppose we have the following crashing data and network information:
Immediate Normal Crash
Activity Predecessor Time (days) Time (days) Normal Cost Crash Cost
A ----85 $500 $800
B A 43 $200 $350
C ----75 $500 $900
D C 42 $200 $500
E B,D 32 $300 $550
Suppose management desires an 11 day project completion time. Formulate a linear programming model that can be used to assist with the crashing decisions. Using this, what activities should be crashed and by how much? What is the total crashing cost?
Upload a copy of the final Excel file used to complete this problem using the Add File selection button below. You will need to calculate the crash cost per day before setting up your linear program.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!