Question: Your boss is the project manager for a large contract assembly plant. She tells you that the learning rate for Product F is 0.87 and
Your boss is the project manager for a large contract assembly plant. She tells you that the learning rate for Product F is 0.87 and that the first unit took 22 hours. You have made 20 units for a customer and now they want another 20.
How long will it take to make the first unit of the second order of the product? Answer to two decimal places.