Question: Your boss is the project manager for a large contract assembly plant. She tells you that the first unit for Product A took 28 hours
Your boss is the project manager for a large contract assembly plant. She tells you that the first unit for Product A took 28 hours and the second one took 23 hours.
What is the learning rate for this Product A? Answer to two decimal places.