Question: Your client asks you for a minor change on your project which you believe will not affect the cost or schedule baseline. What will your
Your client asks you for a minor change on your project which you believe will not affect the cost or schedule baseline. What will your next step be? a) You will implement the request because it will not affect the project. b) You will not implement the request. c) You will review the request with your team members. d) You will inform management.