Question: Your initial plan was to finish all configuration work before testing would start.However, due to some delays, you have decided to start testing even though
Your initial plan was to finish all configuration work before testing would start.However, due to some delays, you have decided to start testing even though configuration isnot yet complete. Which of the following would best describe this situation?
A) You have changed a start to finish relationship to a finish to start relationship.
B) You have changed a finish to start to a start to start relationship.
C) You have changed a mandatory dependency to a discretionary dependency.
D) You have changed soft logic to hard logic.