Question: Your lead software engineer estimates that the remaining coding work will most likely require 8 weeks to complete. It could be completed in 4 weeks

Your lead software engineer estimates that the remaining coding work will most likely require 8 weeks to complete. It could be completed in 4 weeks if the infrastructure improves, but it could take up to 24 weeks if it encounters a higher downtime. What is the expected duration of the code completion using the beta distribution three-point estimate? Group of answer choices 11.5 weeks 6.4 weeks 10 weeks 12.2 weeks