Question: Your lead engineer estimates that a work package will most likely require 5 0 weeks to complete. It could be completed in 4 0 weeks

Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is the PERT estimate for the expected duration of the work package?
a.45 weeks
b.70 weeks
c.90 weeks
d.140 weeks
Group of answer choices
c
d
b
a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!