Question: Your next project consists of 8 sequential 10-day activity estimates, each estimated by a different worker in your organization. You have All secretly added your

Your next project consists of 8 sequential 10-day activity estimates, each estimated by a different worker in your organization. You have All secretly added your own safety margin to come up with your activity estimates and you hear the PM saying *I'm taking your safety margins out of your activity estimates". Now you know the PM is a Goldratt fan, what will the project buffer be?. Choose the closest numeric answer to your calculations