Question: Your options for shipping $ 9 7 comma 8 6 0 9 7 , 8 6 0 of machine parts from Baltimore to Kuala Lumpur,

Your options for shipping
$97 comma 86097,860
of machine parts from Baltimore to Kuala Lumpur, Malaysia, are(1) use a ship that will take
3030
days at a cost of
$3 comma 5703,570,
or(2) truck the parts to Los Angeles and then ship at a total cost of
$4 comma 8404,840.
The second option will take only
2222
days. You are paid via a letter of credit the day the parts arrive. Your holding cost is estimated at
3030%
of the value per year.
If you have a third option and it costs only
$4 comma 0904,090
and also takes
2222
days, what is your most economical plan?
Part 2
The daily holding cost of Alternative 1 is
$enter your response here.
(Enter your response rounded to two decimal places.)
Part 3
The daily cost of faster shipping with Alternative 2 is
$enter your response here.
(Enter your response rounded to two decimal places.)
Part 4
The daily cost of faster shipping with Alternative 3 is
$enter your response here.
(Enter your response rounded to two decimal places.)
Part 5
Alternative 1
Alternative 3
Alternative 2
is more economical.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!