Question: Your organization is implementing an agile approach for the first time, and senior management is asking you for guidance, specifically about the project charter and

Your organization is implementing an agile approach for the first time, and senior management is asking you for guidance, specifically about the project charter and how it differs between traditional predictive projects and agite projects. What would you tell them?
A The project charter in agile is more succinct and allows for continuous updates and changes to requirements.
B
A project charter is not always required for agile projects.
C
Because the product owner is the sponsor of an agile project, they are the one signing the project charter.
D The project charter in agile needs to be revised for each sprint as new user stories are added.
 Your organization is implementing an agile approach for the first time,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!