Question: Your project depends on a key deliverable from a vendor you've used several times before with great success. You're expecting the vendor to finish ahead

Your project depends on a key deliverable from a
Your project depends on a key deliverable from a vendor you've used several times before with great success. You're expecting the vendor to finish ahead of their schedule commitment as they usually do. This is an example of .... a) an assumption b) a requirement c) a constraint d) an objective