Question: Your project has eight activities from Act A, Act B, Act C up to Act H. The duration in days of each activity is as

Your project has eight activities from Act A, Act

Your project has eight activities from Act A, Act B, Act C up to Act H. The duration in days of each activity is as follows: Act A 23, Act B 40, Act C 11, Act D 15, Act E 6, Act F 27, Act G 18, Act H 37. If the predesessor relationships between activities are as per the table below, calculate the latest start date for activity H if the early start of activity A is taken as day 0. Act Predec A B A B Ula B E D IF E,G G H F