Question: Your project is a part of a multi - project program with shared resources which is impacting your project resource availability. You have scheduled a
Your project is a part of a multiproject program with shared resources which is impacting your project resource availability. You have scheduled a meeting with the functional manager to discuss this project risk. What is the focus of your communications with the functional manager?
Group of answer choices
Review of the CrossFunctional Resource Allocation
Review of the Project Plan
Review of the detailed Work Breakdown Structure
Review of the specific Functional Resource Allocation