Question: Your project is currently in the execution phase. In your project, a risk occurs which requires a risk response that impacts the schedule baseline. What

Your project is currently in the execution phase.

Your project is currently in the execution phase. In your project, a risk occurs which requires a risk response that impacts the schedule baseline. What should you do? a. Perform a risk audit b.Issue a change request c. Do nothing d. Review the cost impact