Question: Your project is currently in the execution phase. In your project, a risk occurs which requires a risk response that impacts the schedule baseline. What

  1. Your project is currently in the execution phase. In your project, a risk occurs which requires a risk response that impacts the schedule baseline. What should you do?

    a.

    Perform a risk audit

    b.

    Issue a change request

    c.

    Review the cost impact

    d.

    Do nothing