Question: Your project is progressing and is about halfway completed. You make a point of reviewing the project's performance weekly. Your current review of performance shows

Your project is progressing and is about halfway completed. You make a point of reviewing the project's performance weekly. Your current review of performance shows the following metrics: EV =30,000, AC =28,000, and PV =22,000. What is the cost variance?
Question 10Answer
a.
28000
b.
6000
c.
-2000
d.
-6000
e.
2000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer