Question: Your project sponsor has requested a cost estimate for the project on which you're working. This project is similar in scope to a project you

Your project sponsor has requested a cost estimate for the project on which
you're working. This project is similar in scope to a project you worked on last year.
She would like to get the cost estimates as soon as possible. Accuracy is not her
primary concern, which tool and technique will use for the estimate?
Bottom-up estimating
Parametric estimating
Three-point estimating
Analogous estimating