Question: Your project sponsor has requested a cost estimate for the project on which youre working. This project is similar in scope to a project you
Your project sponsor has requested a cost estimate for the project on which you’re working.
This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decide to use ___________________.
A. analogous estimating techniques B. bottom-up estimating techniques C. parametric estimating techniques D. three-point estimating techniques