Question: Your project team has already created the WBS , developed estimates for the work packages, and sequenced the project activities using the arrow diagramming method.
Your project team has already created the WBS developed estimates for the work packages, and sequenced the project activities using the arrow diagramming method. In addition, your team has applied resource leveling and schedule compression techniques on the project schedule. Which actions should be performed NEXT:
Obtain approval of schedule
Develop activity resource requirements
Initiate schedule change control
Decompose the work packages into smaller components called schedule activities