Question: Your project team has been assigned to develop and launch an it system for a local healthcare company. Use the information in the table below
Your project team has been assigned to develop and launch an it system for a local healthcare company. Use the information in the table below to construct a network diagram using the AON method.
tableActivity IDDescription,Duration daysPredecessorARequirement analysis,BSystems design,ACProgramming,BDTelecoms,BEHardware installation,B D DFIntegration,GGSystem testing,HIHandover and GDlive,
Construct a network diagram using the activityonthenode method.
Conduct the forward and backward passes to calculate your ES EF LS and LF times for each activity.