Question: Your team has a plan to build 100 Custom Game Servers in 10 weeks. The plan is to build 10 Servers per week (10 Servers
Your team has a plan to build 100 Custom Game Servers in 10 weeks. The plan is to build 10 Servers per week (10 Servers per week x 10 weeks = 100 Game Servers)
The plan states that: During the first 5 weeks, it should cost $2,000 each week to build 10 Servers per week. The next 5 weeks it should cost $1,000 each week to build 10 Servers per week because of the efficiency gains. At the end of the 7th week (i.e. finished the 7th week and getting ready to start the 8th week), the team has built 35 servers and team has spent $14,000.
At the end of week 7, what are PV (Planned Value), RP (Rate of Performance), AC (Actual Cost), EV (Earned Value), CV (Cost Variance), SV (Schedule Variance), CPI (Cost Performance Index), SPI (Schedule Performance Index), EAC (Estimate At Completion), and ETC (Estimate Time to Complete)?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts