Question: Your team has identified several risks in the project as well as their probability, impact, and priorities. The team is now exploring the response strategies
Your team has identified several risks in the project as well as their probability, impact, and priorities. The team is now exploring the response strategies to risks if they occur. The team identified that a couple of the programmers on the team might leave, which would significantly impact the project, but they decide to deal with it if and when it occurs. Which one of the following statements is true?
This is passive acceptance.
This active acceptance.
This is risk avoidance.
This is riskmitigation