Question: Your team is currently a bit behind schedule, and the team is worried that it won t complete the work before the iteration ends. If
Your team is currently a bit behind schedule, and the team is worried that it wont complete the work before the iteration ends. If you are practicing good servant leadership, what should you do first?
A Take on administrative work, as needed.
B Communicate with stakeholders.
C Hold standup meetings.
D Coach the team on agile principles.