Question: You're estimating durations for project work activities using parametric estimating. What is the correct formula to use? Select one: a. Quantity of work x productivity
- You're estimating durations for project work activities using parametric estimating.
What is the correct formula to use?
Select one:
a. Quantity of work x productivity rate / number of resources
b. Quantity of work / productivity rate x number of resources
c. Quantity of work - productivity rate x number of resources
d. Quantity of work x productivity rate - number of resources
2 What are the examples of some of the tools and techniques you can use to control your project's schedule?
Select one or more:
a. Redistributing work among resources by adjusting the schedule
b. Realigning activities based on delays or overlap opportunities in the schedule
c. Condensing the project schedule without changing the project scope
d. Using software to monitor target actual start, duration, and completion dates
e. Updating the project schedule to account for potential delays
f. Requesting changes to be made to the schedule management plan