Question: Youre managing a construction project. Youve decomposed work packages into activities, and your client needs a duration estimate for each activity that you come up
Youre managing a construction project. Youve decomposed work packages into activities, and your client needs a duration estimate for each activity that you come up with. Which of the following will you use for this?
a
Activity list
b
Milestone list
c
Critical path analysis
d
Project schedule network diagram