Question: Youre managing a construction project. Youve decomposed work packages into activities, and your client needs a duration estimate for each activity that you came up
You’re managing a construction project. You’ve decomposed work packages into activities, and your client needs a duration estimate for each activity that you came up with. Which of the following BEST describes what you are doing?
A. Evaluating each activity to figure out how much effort it will take B. Estimating the number of person-hours that will be required for each activity C. Understanding, in calendar time, how long each activity will take D. Estimating how many people it will take to perform each activity