Question: You're working on a construction project which requires 800 square meters of tilling. The tiler works eight hours a day and manages to lay 40
You're working on a construction project which requires 800 square meters of tilling. The tiler works eight hours a day and manages to lay 40 square meters of tiles per day. Use parametric estimating