ni Romano is in charge of planning and coordinating the analytics work shop fo nalytics company. Listed below are the activity information (time frames in for the project.
ty Description
Plan event
Select location
Decide on speakers & vendors
Prepare & mail brochures
Update web site
Final check with speakers & vendors 3.5
Registration & hotel reservations 3
Finalize last-minute details
Optimistic (a)
2
2.5
4
2
1.5
3
2
\table[[Most Probable (m) Pessimi,],[3,4],[2,6],[4,4],[4,6],[2.5,3.5],[4,4.5],[3,6],[5,5]]
Question 1
The Expected Time for Activity C is
2 weeks
4 weeks
6 weeks
3 weeks
 z Instructions e problem below and answer the questions that follow.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!