Question: ZUESTION 2 . Jse the Normal time given in Table 2 to reduce the project by 8 days. What is the total added cost? TABLE

ZUESTION 2.
Jse the Normal time given in Table 2 to reduce the project by 8 days. What is the total added cost?
TABLE 2
Time (days) Activity cost (S) Activity Description Predecessor Normal Crash Normal Crash A Excavation, pour footers none 64 $1020 B Lay foundation A 53 $2228 C Frame and Roof B 54 $1522 E Sewer (floor) drains B 32 $2126 F Install insulation C 54 $2530 G Pour basement floor E 53 $1118 I Install windows F 43 $2022 J Rough electrical wiring F 32 $2020 K Install furnace C,G 85 $1130 L Exterior brickwork I 86 $1628 M Install plasterboard J,K 108 $1830 N Roof shingles L 43 $23290 Attach gutter N 52 $2531 P Grading 073 $1216 Q Lay subflooring M 54 $1725 R Lay driveway P 86 $2030 T Kitchen, sink, appliances Q 86 $1228 V Painting T 86 $1024 W Finish wood floor V 86 $2531
To receive credit, you must enter your answers in the table provided;
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Day 8
 ZUESTION 2. Jse the Normal time given in Table 2 to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!