Question: The collect requirements process is important for tracking requirements. However, which of these is not an input? a) Scope management plan b) Requirements management plan

The collect requirements process is important for tracking requirements. However, which of these is not an input?

a) Scope management plan

b) Requirements management plan

c) Stakeholder management plan

d) Enterprise environmental factors