Question: Which document is considered to be the most important for the go-ahead approval of a project? a) The business case b) The solution scope c)

Which document is considered to be the most important for the go-ahead approval of a project?

a) The business case

b) The solution scope

c) The enterprise analysis

d) The requirement specification