Question: You are working through your projects risk and are analyzing probability and impact. What kind of analysis are you most likely conducting? a) Qualitative risk
You are working through your project’s risk and are analyzing probability and impact. What kind of analysis are you most likely conducting?
a) Qualitative risk assessment
b) Quantitative risk assessment
c) Risk register update
d) Risk assessment