Question: 3-4 The normal time for processing orders in a warehouse is given as 35.120 hours per 100 orders. It is estimated that unavoidable delays will

3-4 The normal time for processing orders in a warehouse is given as 35.120 hours per 100 orders. It is estimated that unavoidable delays will account for 20 percent of the total time and that labor efficiency will be 90 percent. What will be the standard time per order? The actual time? (Ans. 0.439, 0.488)