Question: Activity Immediate Predecessor Optimistic Most Likely Pessimistic A 4 6 8 B 1 2 3 C A 4 4 4 D A 4

Activity Immediate Predecessor Optimistic Most Likely Pessimistic A — 4 6 8 B — 1 2 3 C A 4 4 4 D A 4 5 6 E B 7 10 16 F B 8 9 10 G C 2 2 2 H D,E,G 2 3 7 I F 1 3 11