The following data are given for a single processor, static job shop:

Job 1 2 3 4 5 6 Processing time 3 2 9 4 2 4 Due date 17 21 5 12 15 24

a. Give a schedule that minimizes the average flow time. What is the average flow time for your schedule?

b. Give a schedule that minimizes maximum tardiness. What is the maximum tardiness for your schedule?

c. Give a schedule that minimizes the number of tardy jobs. How many jobs are tardy in your schedule?