Question: A quality-control apprentice is preparing a CUSUM chart. The values calculated for SL and SH are presented in the following table. Three of the values
A quality-control apprentice is preparing a CUSUM chart. The values calculated for SL and SH are presented in the following table. Three of the values have been calculated incorrectly. Which are they?
Previous results suggest that a value of ???? = 15 is reasonable for this process.
a. Using the value 1500 for the target mean ????, and the values k = 0.5 and h = 4, construct a CUSUM chart.
b. Is the process mean in control? If not, when is it first detected to be out of control?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts